TICAD IV Follow-up Mechanism Annual Progress Report 2009
Annual Progress Report 2008  Annual Progress Report DIGEST 2009
JapaneseFrench

SectorsImplementing PartnersCountriesReporting Years

GoJ(MOFA):Provide funds of US$3 million for 2008
ICRC: Implement water and sanitation programme

Yokohama Action Plan
[1]Promote the development of water and sanitation facilities with affordable technologies.
[2]Support capacity building of managers and users of water and sanitation system and promote awareness raising campaigns to improve hygiene practices including hand washing.
Proposed Measures by Japan/Implementing Partners
● Promote the development of water and sanitation facilities, support capacity building of managers and users of water and sanitation system and improve hygiene practices.
Potential Resources, Possible Contributions
GoJ(MOFA):Provide funds of US$3 million for 2008
ICRC: Implement water and sanitation programme
Implementing Partners
GoJ(MOFA)/ICRC
Related Links

Current Status of Implementation 2008

Country
Central African Republic/DRC
Status
Completed
(i) Central African Republic
(a)Installed some 1,000 public and household latrines, built or rehabilitated 62 water points, repaired 50 hand pumps and drilled 26 wells. (b)In parallel, the residents of 259 villages were coached on hygiene practices and National Society personnel were also trained to ensure maintain water points. (c)180,000 people benefited from the projects.

(ii)DRC
(a)Water-trucking was undertaken to adress the daily water needs of IDPs living in such as overcrowded camps or ill-equipped public buildings in the Kivus. (b)Rural and urben water facilities were installed, rehabilitated or maintained lowering helth risks of the residents and IDPs in Katanga and the Kivus. Water systems were installed or rehabilitated in 14 villages. (c)The urban water and electricity boards received ICRC logistical and technical support to improve water supply infrastructure in three towns. (d)624,190 people benefited from the projects.
More information
【More information (i)】http://www.icrc.org/Web/eng/siteeng0.nsf/html/annual-report-2008-car other site
【More information (ii)】http://www.icrc.org/Web/eng/siteeng0.nsf/html/annual-report-2008-drc other site