| April 2003 |
|
Sector / Name of Project |
Estimated Cost |
Project Description |
Note |
|
I-Education Sector |
|||
| Junior High Schools Construction Project | 134.62 |
- Construction of junior high schools - Procurement of relevant equipment |
|
| Construction and equipment of higher education institutions | 50.12 |
- Construction of higher education institutions at the regional level - Reinforcement of the technical capability of the existing institutions |
Technical studies needed |
|
II-Formation Sector |
|||
| Installation and development of apprenticeship/ restructuring and development of vocational training | 43.10 |
- Construction of training centers - Procurement of training equipment - Preparation of specialized training programs |
- F/S and E/S available - JICA requested for a development study |
|
III-Sewerage Sector |
|||
| Sewerage Construction Project for 6 cities (Tiflet, Tahala, Berrechid, Khouribga, Khémisset, Sidi Kacem) | 70.17 |
- Rehabilitation of the existing waste water network - Extension of waste water networks - Interception works of the waste water to water treatment plants - Construction of water treatment plants |
- M/P available - D/D underway |
|
IV-Energy and Mining Sector |
|||
| The global electrification program in rural area (PERG) (The 4th Phase) | 400.96 |
- Electrification of 300,000 homes in rural area from now to 2006 | - D/D underway - FY 1998 and 2002 Yen loan for the second and third phases |
|
V-Highway Sector |
|||
| Settat-Marrakech Expressway Construction Project (Section Skhour Rhamna-Marrakech) | 210.50 |
- Construction of the Skhour Rhamna-Marrakech Expressway (84km) | - F/S and D/D underway - EIA available |
|
VI-Forest Sector |
|||
| Catchment Area Reforestation Project | 50.12 |
- Environment protection uphill of dams - Protection of dams from mud - Tackling erosion - Preservation of natural resources - Improvement of population income - Socio-economic development of the concerned areas |
- National Scheme of basin sides development available - F/S available |
|
VII-Health Sector |
|||
| Public Hospital Rehabilitation Project | 60.14 |
- Rehabilitation of public hospitals - Procurement of relevant equipment |
- Technical information on standard equipment available - Technical studies needed |
|
VIII-Water Resources Sector |
|||
| Bouregreg Water Treatment Plant Extension Project in Rabat | 22.05 |
- Extension of the water treatment plant to increase the flow by 2m3 per second (first phase) | - F/S available |
| Rural Cities Drinking Water Supply Project (Beni Mellal, Tétouan and Essaouira ) | 46.21 |
- To supply drinking water from the Bin El Ouidane dam (Beni Mellal) and Raouz dam (Tétouan) and from Meskala resources (Essaouira), as well as the desulphurization, demineralization and construction of a water tank | - F/S underway |
| Implementation of the ozonization and filtering installations in the Bouregreg complex | 60.14 |
- Ozonization and filtration for the treatment of a flow of 13m3 per second by carrying out pre-ozonization and inter-ozonization work | - F/S available |
| F/S: Feasibility Study D/D: Detailed Design E/S: Execution Study EIA: Environmental Impact Assessment M/P: Master Plan 1MDH=0.10024 US$=12 yen
|